Title:Request for proposals : development of a master plan, transmission line routing study, and environmental impact statement for Hawaii's proposed geothermal/inter-island cable project
Authors:Department of Business and Economic Development, State of Hawaii
Keywords:engineering
Hawaii
Hawaii Deep Water Cable Program
LC Subject Headings:Environmental impact statements--Hawaii
Cables, Submarine--Hawaii
Electric power transmission--Hawaii
Electric lines--Hawaii
Electric cables
show 2 moreUnderground electric lines--Hawaii
Requests for proposals (Public contracts)--Hawaii
show less
Date Issued:10 Mar 1989
Publisher:Department of Business and Economic Development, State of Hawaii
Citation:Department of Business and Economic Development, State of Hawaii. 1989. Request for proposals: Development of a master plan, transmission line routing study, and environmental impact statement for Hawaii's proposed geothermal/inter-island cable project. Honolulu (HI): Department of Business and Economic Development, State of Hawaii.
Abstract:This letter is to invite your proposal to prepare a Master Development Plan, conduct a public involvement program, conduct an evaluation of overland transmission corridors and prepare a routing report, conduct a public involvement program, and prepare an Environmental Impact Statement for the development of 500 megawatts (net) of geothermal resource in the Kilauea East Rift Zone on the Island of Hawaii and transmit it to Maui and Oahu via an inter-island electrical transmission system. The Master Development Plan is desired by the end of 1989. It is expected that the location and selection of overland transmission line corridors will take place in 1989, with the preparation of routing report to be completed in 1990. It is expected that this routing study be conducted with the full benefit of a public involvement program. With the completion of the master plan and routing work, the State desires an Environmental Impact Statement which will lead to the permitting of the project. Permitting assistance will be requested as a separate additive proposal item under this solicitation.
Proposals are due no later than April 13, 1989.
The attached Notice of Intent to Respond is due no later than March 29, 1989.
Attached, for your information and use, is a brief description of the purpose and intended scope of this project.
Pages/Duration:23 pages
URI:http://hdl.handle.net/10524/33557
Appears in Collections: The Geothermal Collection


Please email libraryada-l@lists.hawaii.edu if you need this content in ADA-compliant format.

Items in ScholarSpace are protected by copyright, with all rights reserved, unless otherwise indicated.