Please use this identifier to cite or link to this item: http://hdl.handle.net/10524/36061

Hawaii Deep Water Cable (HDWC) Program : cable overloadability study

Item Summary

Title: Hawaii Deep Water Cable (HDWC) Program : cable overloadability study
Authors: Pirelli Cable Corporation and Societa Cavi Pirelli
Keywords: cable
demonstration
capacity
engineering
Hawaii
LC Subject Headings: Cables, Submarine--Hawaii
Electric power transmission--Hawaii
Electric lines--Hawaii
Electric cables
Issue Date: Mar 1986
Publisher: Pirelli Cable Corporation and Societa Cavi Pirelli
Citation: Pirelli Cable Corporation and Societa Cavi Pirelli. 1986. Hawaii Deep Water Cable (HDWC) Program: cable overloadability study. Pirelli Cable Corporation and Societa Cavi Pirelli.
Abstract: The scope of this study is to determine the short term overload capability of Cable No. 116 in the event of the loss of one pole of the dc transmission system. Such a loss would result in the loss of 250 MW of transmitted power. This exceeds the spinning reserve capability of the Hawaiian Electric Company on Oahu. The maximum allowable first contingency power loss which can be accomodated by the available spinning reserve while maintaining the integrity of the system is 125 MW. The loss of one pole of the dc system would therefore require an increase of 50 percent in the transmitted power on the remaining pole for a period of time up to 4 hours. The surviving pole conductor during this period must therefore carry 150 percent of rated power, i.e. 375 MW corresponding to 1250 amps. The findings are included in this report.
Pages/Duration: 78 pages