Item Description Chen, Bill H. en_US Lopez, Louis P. en_US Kuwada, James T. en_US Farrington, Ray J. en_US 2012-02-29T20:53:32Z 2012-02-29T20:53:32Z 1980-09 en_US
dc.identifier.citation Progress report on HGP-A wellhead generator feasibility project. Chen BH, Lopez LP, Kuwada JT, Farrington RJ. 1980. Geothermal Resources Council, Transactions 4 (September 1980): 491- 494. en_US
dc.description Geothermal Resources Council, Transactions Vol. 4, September 1980 en_US
dc.description.abstract The HGP-A Well underwent a substantial workover last fall. A new tie-back 7" casing was installed from surface to 3,000 ft. A two-week test was conducted in January, 1980, with full hydrogen sulfide and noise abatement. Preliminary test results showed a slight increase in total mass flow. Both noise and odor abatement were shown to be very effective. As a result of the two-week test, some changes have been made to the final design, and the projected plant on-line date has been extended to 3/31/80. en_US
dc.description.sponsorship Department of Energy Contract DE-AC03-78ET28420, State and County of Hawaii, and Hawaii Electric Light Company en_US
dc.format.extent 4 pages en_US
dc.language.iso en-US en_US
dc.publisher Research Corporation of the University of Hawaii en_US
dc.publisher Rogers Engineering Co., Inc. en_US
dc.subject reservoir engineering en_US
dc.subject reservoir assessment en_US
dc.subject Puna en_US
dc.subject Kilauea East Rift Zone en_US
dc.subject Hawaii Island en_US
dc.title Progress report on HGP-A wellhead generator feasibility project en_US
dc.type Report en_US
dc.type.dcmi Text en_US

Item File(s)

Files Size Format View
Progress Report ... as. Project Sept. 1980.pdf 1.904Mb PDF View/Open

This item appears in the following Collection(s)

Show simple item record


Advanced Search


My Account